You are here:  Home Projects Airport & Aviation Services (Sri Lanka) Limited

Ongoing Projects (AA)

Ongoing projects on 30.06.2016

Project Name

Runway Overlay & Associated works at BIA

Estimated Cost (Rs.Mn.)

AASL - 156 , FA-9,188

Progress

For both construction & consultancy contract-financial proposals were evaluated & negotiation was in progress


Project Name

Walkways Refurbishment (a. Departure walk ways   b. Arrival walkway)

Estimated Cost (Rs.Mn.)

AASL-285

Progress

Arrival walkways contract was awarded on 27.05.2016. Departure walkways bid evaluation completed & report sent for MPC meeting scheduled on 04.07.2016


Project Name

Expansion of departure public concourse & garden shops

Estimated Cost (Rs.Mn.)

AASL-255

Progress

Bids opened on 14.06.2016 & Bid evaluation was in progress.


Project Name

Check-in area expansion

Estimated Cost (Rs.Mn.)

AASL-1000

Progress

Feasibility study


Project Name

Emigration area re-development-Departure

Estimated Cost (Rs.Mn.)

AASL-300

Progress

Layout drawing of the new emigration area was finalized with the consent of immigration officers. Structural designs in progress.Some Architectural drawings to be amended. New floor to be added in order to accommodate A/C requirements and Structural designs to be re-done accordingly.


Project Name

Electronics mall & immigration area modification.

Estimated Cost (Rs.Mn.)

AASL-400

Progress

Clarification from the Bidders for Bid evaluation.


Project Name

Installation of ADS-B Ground Stations.

Estimated Cost (Rs.Mn.)

AASL-220

Progress

  • Site Survey conducted.
  • Design 90% completed.
  • FAT & Training scheduled.
  • Manufacturing commenced.


Project Name

Supply, Installation and commissioning of Aeronautical HF Transmitters with antennas at HF transmitting station - Attidiya

Estimated Cost (Rs.Mn.)

AASL-220

Progress

Bids evaluated & initial report has been submitted to CAPC.


Project Name

Supply, Installation and commissioning of Air Traffic Management (ATM) System at BIA.

Estimated Cost (Rs.Mn.)

AASL-320

Progress

Amendments to the specifications are being carried out.


Project Name

Supply, Installation and commissioning of Aeronautical Information Management (AIM) System

Estimated Cost (Rs.Mn.)

AASL-260

Progress

Bidding document is at Scrutinization stage.


Project Name

Upgrading of Communication Systems at BIA & RMA

Estimated Cost (Rs.Mn.)

AASL-420

Progress

Awaiting Cabinet decision for project approval in principle.


Project Name

New Navigational Services Building at BIA

Estimated Cost (Rs.Mn.)

AASL-200

Progress

Design scrutinized. Re-drafting bidding document.


Project Name

Construction of a New Communication Link Building at BIA.

Estimated Cost (Rs.Mn.)

AASL-80

Progress

Re-designing the building.


Project Name

Expansion to Control Tower Cabin-BIA.

Estimated Cost (Rs.Mn.)

AASL-120

Progress

Requirement study and designing.


Project Name

Modernisation of Aero Mobile Centre (HF Communication).

Estimated Cost (Rs.Mn.)

AASL-100

Progress

Drafting of bidding documents.


Project Name

Balance work of Gr.1 & Gr.11 Quarters at MRIA.

Estimated Cost (Rs.Mn.)

AASL-63

Progress

Contract awarded & Construction in progress.

Project Name

a) Package A- Main Terminal Building, Pier No.02 & Elevated Road way Package C-Pier No 03, Multi Storied Car Park, etc

b) Package B - Apron, Taxi way & Utilities

Estimated Cost

a) FA-JPY 74397

b) included in the above cost

Progress

a) Package A Bidding documents submitted to Chairman CAPC on 24.06.2016

b) CAPC convened on 12.4.2015 approved bidding document Tender briefing was held on 5.8.2016.

Project Name

a) Detailed Design and Post Design Consultancy Services.

b) Renovation of Arrival Walkways at the Terminal Building, Bandaranaike International Airport Katunayake

Progress

a) Negotiation for the contract amendment concluded on 23.6.2016.